On June 6 and June 13, the Bronxville Board of Education accepted donations from the Bronxville School Foundation that allowed the district to move forward with the long-awaited Phase II of the Chambers Field Project. This phase encompasses construction of a new concession stand, installation of new bleachers, and a press box.  The Board awarded contracts for this work to Caladri Development Corporation, who honored the bids placed last fall.

Although Phase II was conceived as an extension of the original turf project, there were design issues, low budget estimates, and high bids that led to postponements of the work.  The grants from the Bronxville School Foundation made it possible to carry out the entire scope of work.  Like the turf field, Phase II is entirely supported by private donations.

The Foundation made an initial donation of $72,000 in 2009, adding to the $170,000 balance remaining in the turf field project account.  The recent grant of $82,000 bridged the gap between the budget estimate and the actual bid for the concession stand/restroom. The additional $200,000 gift accepted in June allows the bleachers and press box to be included in the scope of work. Construction is expected to begin in the near future with an expectation of completion by the fall.

Other Facilities News:

In order to advance the schedule of the auditorium/science lab renovations, the District's design team obtained early approval and waivers from the labor department to undertake an attic abatement project in the summer of 2013.  This work will alleviate pressure on next year's schedule and make it more likely that the science lab renovations can be completed with minimum disruption.